Delays dog U.S. government loans to green energy projects
A year after the
U.S. government raced to meet a deadline to finish loan agreements with
dozens of clean energy companies, less than half the total money
promised has been handed over.
Technical questions and companies' own failures in hitting contractual milestones are behind some of the holdups.
But
government officials fearful of taking a risk on firms that could
collapse may have also caused some of the delays. The political
firestorm after the failure of Solyndra, a solar panel maker that went
bankrupt last year after receiving more than $527 million in a
government loan, may have made the authorities wary, industry experts
and investors say.
The Energy
Department and some companies say the pace of disbursement reflects an
appropriately cautious approach to handling taxpayer investment in
nascent industries. In some cases, though, the rigid approval process
for drawing on loans has frustrated recipients, who feel the government
is withholding cash due to minor setbacks.
A
Reuters analysis of Treasury Department data on payments to 19 solar,
wind and geothermal power projects of the 26 in the Energy Department's
portfolio shows that the pace at which funds have been released has been
slow and uneven. Funding for the other seven loans, amounting to a
combined $5.6 billion, comes from private lenders, with the Energy
Department guaranteeing 80 percent of the principal. The department
declined to discuss these loan disbursements.