A judge in Lamar County, Texas, ruled Wednesday night that
TransCanada’s Keystone XL pipeline has the right of eminent domain,
rejecting a plea by farm manager Julia Trigg Crawford and dealing a blow
to landowners and environmentalists who have been trying to block
construction of the pipeline.
The ruling by Judge Bill Harris removes yet another potential obstacle for TransCanada, which already has permits from the Army Corps of Engineers for the southern leg of the pipeline, which starts in Cushing, Okla., and runs to Port Arthur, Texas. TransCanada has said it will start building as soon as possible.
In March, President Obama endorsed the construction of the southern leg of the pipeline. He said it would alleviate a supply bottleneck at Cushing, where the benchmark price of oil is set for the U.S. market.
But environmental groups and some landowners have been mounting a campaign to stop or delay construction because of the threat a leak might pose to rivers and wetlands.
Crawford had asserted that the Keystone XL pipeline was not entitled to eminent domain because the pipeline would not be a common carrier, open to a variety of oil companies. She said that as a private project, it needed to negotiate rights of way without compelling landowners to enter agreements.
Usually the option of using eminent domain for pipelines is granted by state agencies; in Texas, it is recognized by the Texas Railroad Commission, a long-time regulator of the state oil industry.
Read more: http://www.washingtonpost.com/business/economy/texas-judge-rules-in-favor-of-transcanada-in-eminent-domain-case/2012/08/23/87744776-ecda-11e1-a80b-9f898562d010_print.html
The ruling by Judge Bill Harris removes yet another potential obstacle for TransCanada, which already has permits from the Army Corps of Engineers for the southern leg of the pipeline, which starts in Cushing, Okla., and runs to Port Arthur, Texas. TransCanada has said it will start building as soon as possible.
In March, President Obama endorsed the construction of the southern leg of the pipeline. He said it would alleviate a supply bottleneck at Cushing, where the benchmark price of oil is set for the U.S. market.
But environmental groups and some landowners have been mounting a campaign to stop or delay construction because of the threat a leak might pose to rivers and wetlands.
Crawford had asserted that the Keystone XL pipeline was not entitled to eminent domain because the pipeline would not be a common carrier, open to a variety of oil companies. She said that as a private project, it needed to negotiate rights of way without compelling landowners to enter agreements.
Usually the option of using eminent domain for pipelines is granted by state agencies; in Texas, it is recognized by the Texas Railroad Commission, a long-time regulator of the state oil industry.
Read more: http://www.washingtonpost.com/business/economy/texas-judge-rules-in-favor-of-transcanada-in-eminent-domain-case/2012/08/23/87744776-ecda-11e1-a80b-9f898562d010_print.html